Preventive Maintenance
Prepare the MCE Access Form, obtain LTA endorsement, notify OCC and arrange keys/cards.
View PM process ↓A practical guide for PM, CM, tunnel and room access, key collection, road-shoulder stops and lane closures at the Marina Coastal Expressway.
Choose the work type before starting an application. Timing and approvals differ substantially.
Prepare the MCE Access Form, obtain LTA endorsement, notify OCC and arrange keys/cards.
View PM process ↓Notify the relevant LTA/OCC contact, confirm personnel access, collect the required key and proceed.
View CM process ↓For quick loading or unloading. StarHub coordinates with LTA. This is not a lane closure.
View stop process ↓Engage Gim Tian to coordinate the closure with LTA and support the EMAS and eRMS process.
View closure process ↓Complete the KPE/MCE Authorisation Form for Access with the location, chainage or niche, work period, required keys/cards, work description, safety precautions, operational impact and Site OIC details.
Include the MOS, workers list and any applicable declaration.
Send the completed draft to StarHub. A StarHub representative must complete the Requested by details and add the signature, date and company stamp.
Only after StarHub endorses the form, email it to Peter PEH and Kia Heng KANG. Copy the relevant StarHub and ROOTS personnel and state the planned PM dates.
Send the approved or relevant form to OCC through WhatsApp, including the planned work and the keys or cards required.
WhatsApp OCC before the work and include:
This is an additional requirement whenever personnel enter the MCE tunnel.
For planned PM, prepare and submit the MCE Access Form, notify OCC, request the TER key, collect it from L1 Security, complete the work and return the key.
For CM, follow the corrective-maintenance procedure above.
Request the corresponding key when notifying OCC. Provide the form or access details, collect the key, complete the work and return it.
If the access point leads into the tunnel, OCC check-in and check-out are still mandatory.
Use only for a quick vehicle stop to drop off, unload or load equipment.
Required when the work cannot be carried out safely without closing a traffic lane. The closure must be carried out by LTA-approved contractors whose personnel have completed the required LTA lane-closure course.
Keep the signed MCE Access Form available for LTA inspection.
Attach the MOS, workers list and applicable declarations.
Submit any applicable declaration and brief all involved workers on the relevant requirements.
Hot work is strictly prohibited inside the MCE tunnel.
Do not call this number.
Road-shoulder loading / unloading coordination
Access forms; copy on endorsed EMAS notifications
Access forms, EMAS notifications and eRMS coordination
Never enter the MCE tunnel before completing OCC check-in.
Open OCC work access ↗